Sewer Construction Update:

Sewer Construction Update:
• Work will continue with alternating traffic with police details and signage during the hours of 7am -5pm daily. 
• The contractor will finish the sewer forcemain on Phillips Street. 
• They will complete the rest of the service laterals Brown Street and Phillips Street. 
• Work on West Main Street will only come after Brown and Phillips Streets are done, beginning with installing service laterals. West Main Street will be open during this work.