Wickford Sewer Construction Update for the upcoming week September 11

  • The contractors will finish installing the long and short sewer service laterals on Brown Street.
  • The contractor will be working on the sewer forcemains at the intersection of Brown and Phillips Streets and sewer laterals on Phillips Street.
  • There will be alternating traffic Monday through Friday during the hours of 7am -5pm daily.