Wickford Sewer Update Week Ending 11/1/17

 

  • There will be alternating traffic briefly on West Main Street near Newtown Avenue while the contractors restore the drainage culvert across West Main Street.
  • The contractor will be testing the low pressure forcemain on Brown and Phillips Street. The work will mainly impact the sidewalks where the shut-offs are located.
  • Most of the construction work in downtown Wickford will end for the season by the 17th. There will be one half-day of alternating traffic on West Main Street at Newtown Avenue for the water line, but that will take place the week after next or more likely after Thanksgiving.
  • Work will continue on Newtown Avenue and the pump station in Wilson Park.

 

Please don’t hesitate to contact me, Phil Bergeron (pbergeron@northkingstown.org) or Joel Burke (jburke@northkingstown.org) if you have any questions or concerns.

 