Wickford Sewer Update Week Ending 11/25/17

There will be no work on Thursday or Friday.

 

  • The contractor has put leveling course on a portion of West Main Street. This is not the final pavement; it is just to smooth out the roughest section of the road for the winter. The contractor will fully pave West Main (up to Cranston Funeral Home), Phillips and Brown Streets edge to edge in the spring. The rest of West Main is scheduled to be paved to Post Road by the end of the summer.
  • Construction work in downtown Wickford is done for the season.
  • Work will continue on Newtown Avenue and the pump station in Wilson Park.